A Louisiana appeals court upheld the city’s approval of a special use permit for a proposed data center in west Shreveport on November 18. The Second Circuit Court of Appeal affirmed a Caddo Parish district court judgment that left the City Council’s decision in place.

The proposal covers about 254 acres at Resilient Technology Park off Greenwood Road. Bohler Engineering applied in October 2025 for seven data center buildings of 400,000 square feet each, along with support facilities including water storage and an electrical substation. The site is zoned for light industrial use as part of a planned development, but its proximity to land zoned for homes required a special use permit.

The Metropolitan Planning Commission denied the application after a tied vote on December 3, 2025. On December 18, the City Council unanimously reversed that decision and approved the permit and site plan. Three plaintiffs challenged the approval, raising questions about how local development standards were applied. The court record notes that residents also raised concerns about water and electricity demand, traffic and noise during the project review.

The appellate court said its job was to decide whether the council’s approval was arbitrary or capricious, not to substitute its own planning judgment. It found that the record showed the council had enough information to consider the applicable standards, including how the facility would operate, even without a separately labeled operating plan.

The ruling resolves this appeal in the city’s favor, but the opinion notes that a rehearing can be requested. The planning staff report cited by the court calls for a traffic impact study before a building permit is released and separate approval for a proposed extension of Bert Kouns Industrial Loop. The ruling does not announce a construction start or establish that the project has received every other approval it may need.