NEW ORLEANS: Both HOV lanes on the Crescent City Connection reopened November 8, a day ahead of schedule, state transportation officials said Tuesday.

Three lanes heading from the Westbank to the Eastbank are open around the clock. The far right lane remains closed for repairs, according to DOTD’s November 10 announcement.

The HOV lanes have resumed their normal schedule. Concrete barriers are in place, ending overnight closures of the two right lanes.

The $6.5 million project includes cleaning steel, reinforcing connections and adding a protective coating. The closed lane provides equipment space and access to the bridge’s outer steelwork.

DOTD plans to reopen that lane temporarily January 29, 2027, for Mardi Gras, then close it again afterward. Weather can affect the work.

Check Louisiana 511 before traveling and allow extra commuting time.