ST. CHARLES PARISH, La.

Entergy Louisiana estimates its Waterford 5 natural gas plant in St. Charles Parish will cost $1.755 billion, about 63% more than the $1.079 billion estimate it originally filed with state regulators.

Entergy said in a Nov. 12 filing with the Louisiana Public Service Commission that it received a permanent air permit from the Louisiana Department of Environmental Quality and gave its contractor full notice to proceed on Oct. 2. The filing reports progress through Sept. 30 and separately notes those October milestones.

The contractor has been preparing the site since Entergy awarded the engineering, procurement and construction contract in December 2025, the utility said. Entergy reported about $271.7 million in Waterford 5 spending through Sept. 30. Detailed construction progress figures for the plant were not yet available in the public report.

Waterford 5 is one of three generating units in the Laidley project, which the commission approved in 2025 to support Meta’s data center in Richland Parish. The other two units are at Franklin Farms in Richland Parish. Entergy now forecasts about $4.36 billion for the overall generation and transmission project, compared with about $3.96 billion originally filed.

The $676 million difference for Waterford 5 compares the latest forecast with the original filing. It is not a quarterly increase. The report lists no material changes in the cost to complete the Laidley project during the reporting period.